    Portal Powerhouse - Temporary backing to reduce vibration in 3/8" plate bulkhead in turbine Wye branch inadequate; it was replaced with concrete disc back by I-beams.

    photCL SCE 02 - 43898

  • Portal Powerhouse

    Portal Powerhouse

    Visual Materials

    Portal Powerhouse - 12' diameter pipe installed to reduce pressure at portal during high flows. At time, the lower baffle was still there at outlet restricting end area.

    photCL SCE 02 - 43917

  • Portal Powerhouse - Forebay

    Portal Powerhouse - Forebay

    Visual Materials

    Portal Powerhouse - Forebay - Installing 6" dia. drain in foundation, sluice pipe area, prior to any fill. Note form for concrete cutoff around pipe. One of three installed.

    photCL SCE 02 - 43323

  • Portal Powerhouse

    Portal Powerhouse

    Visual Materials

    Portal Powerhouse - Placing concrete in supporting wall under end of 12' diameter pipe. Excavating old concrete anchor. [Forming new] foundation & Wye branch anchor.

    photCL SCE 02 - 43529

  • Portal Powerhouse

    Portal Powerhouse

    Visual Materials

    Portal Powerhouse - View of forming for substructure concrete, showing neat excavation in tight decomposed granite for the draft tube encasement.

    photCL SCE 02 - 43623

  • Portal Powerhouse

    Portal Powerhouse

    Visual Materials

    Portal Powerhouse - Final leveling of Scroll Case prior to concrete encasement.