Portal Powerhouse - Forebay
You might also be interested in

Portal Powerhouse - Forebay
Visual Materials
Portal Powerhouse - Forebay - Progress picture showing placement of upstream impervious fill in sluice pipe area, to top of 24" sluice pipe concrete encasement.
photCL SCE 02 - 43327

Portal Powerhouse - Forebay
Visual Materials
Portal Powerhouse - Forebay - Completed concrete encasement around 24" diameter sluice pipe through rock fill downstream section.
photCL SCE 02 - 43536

Portal Powerhouse - Forebay
Visual Materials
Portal Powerhouse - Forebay - First rock fill in sluice pipe area. Note silty surface mud being pushed immediately ahead of placement rock.
photCL SCE 02 - 43324

Portal Powerhouse - Forebay
Visual Materials
Portal Powerhouse - Forebay - Placing first fill in impervious section under location of sluice pipe. Note dozer pushing layer of saturated & disturbed surface material, exposing firm foundation, before fill placement.
photCL SCE 02 - 43315

Portal Powerhouse - Forebay
Visual Materials
Portal Powerhouse - Forebay - Sluice pipe intake.
photCL SCE 02 - 43813

Portal Powerhouse - Portal Forebay
Visual Materials
Portal Powerhouse - Portal Forebay - Downstream side of dam showing outlet end of 24" sluice pipe.
photCL SCE 02 - 43786