Visual Materials
Borel Powerhouse - Borel 3rd Stage - Tilley #3
You might also be interested in

Borel Powerhouse - Borel 3rd Stage - Tilley #3
Visual Materials
Borel Powerhouse - Borel 3rd Stage - Tilley #3 - Photos showing dismantlement of steel flume sheets.
photCL SCE 02 - 40077

Borel Powerhouse - Borel 3rd Stage - Tilley #3
Visual Materials
Borel Powerhouse - Borel 3rd Stage - Tilley #3 - Preparation for support for floor slab in concrete box flume. Excavation through bulkhead at north end for new bulkhead and open transition.
photCL SCE 02 - 40075

Borel Powerhouse - Borel 3rd Stage
Visual Materials
Borel Powerhouse - Borel 3rd Stage - Progress of Tilley #3 Flume showing steel reinforcment for concrete floor.
photCL SCE 02 - 40084

Borel Powerhouse - Kern River - Borel 3rd stage
Visual Materials
Borel Powerhouse - Kern River - Borel 3rd stage - Shows work accomplished on construction of new concrete flume at Tilley #3 prior to canal outage when steel flume can be removed. Concrete piers raised and backfilled for floor slab support with the exception of two center spans which were left open for drainage.
photCL SCE 02 - 40043

Borel Powerhouse - Borel 3rd Stage
Visual Materials
Borel Powerhouse - Borel 3rd Stage - Refugio Flume (old)
photCL SCE 02 - 40089

Borel Powerhouse - Borel 3rd Stage
Visual Materials
Borel Powerhouse - Borel 3rd Stage - Progress picture after dismantlement of wood structure.
photCL SCE 02 - 40073