Visual Materials
This picture of Dam #1 taken in February 1913
You might also be interested in

Work crews pouring an eastern "wing wall" extension to Dam #1
Visual Materials
By May of 1913, each of the three dams at the Basin was virtually complete. Here, work crews are pouring an eastern "wing wall" extension to Dam #1. By this time, with much of the original "Basin Railroad" flooded by the rising waters of the reservoir, a two-foot narrow-gauge tramway was being used to deliver mixed concrete to each work face.
photCL SCE 12 - 00040

Photo shows the complex system of railroads and chuting employed to pour concrete the dams at Huntington Lake
Visual Materials
Photo shows the complex system of railroads and chuting employed to pour concrete the dams at Huntington Lake. Steam locomotives ran trains of three-yard dump cars from the mixing plant to each dam site. At the dam site the standard gauge trains dumped their concrete into one-yard dump cars that were pulled onto the dam on a narrow gauge track with a gasoline powered locomotive.
photCL SCE 12 - 00067

Big Creek Dam 3
Visual Materials
Big Creek Dam 3 - Showing trestle on top of present dam to be used for pouring concrete down stream side, also trestle in front of present dam; concrete chutes, gravel bunkers, hoist line to bunkers, etc.
photCL SCE 03 - 00788

Big Creek Huntington Lake Dams - Dam #1 - lower face
Visual Materials
Big Creek Huntington Lake Dams - Dam #1 - lower face. [Close-up of the eroded surface of concrete].
photCL SCE 02 - 18840

Big Creek, Huntington Lake Dams - Dam #1
Visual Materials
Big Creek, Huntington Lake Dams - Dam #1 - Upstream face gunite; note debris freshly fallen from concrete above ginite. T. M. Leps
photCL SCE 02 - 40249

Upstream core drill hole Dam 1
Visual Materials
Upstream core drill hole Dam 1. U-s station 10+62.7. Elevation 6898.9. This hole is in column of concrete near gate house which shows evidence of different mix than surrounding concrete on upstream face.
photCL SCE 02 - 20101