Skip to content

Visual Materials

December 1983 saw work begin on the Access Tunnel



You might also be interested in

  • In December 1985. the Balsam Meadow Project reached its halfway mark with the "holing through" of the Tailrace Tunnel

    In December 1985. the Balsam Meadow Project reached its halfway mark with the "holing through" of the Tailrace Tunnel

    Visual Materials

    In December 1985, the Balsam Meadow Project reached its halfway mark with the "holing through" of the Tailrace Tunnel. Here, surrounded by solid granite 400 feet below the snow-covered Sierras, Edison's Balsam Meadow Project Manager Don Brundage (right), congratualtes Dillingham-Atkenson Project Manager Richard L. Kunz on completion of the final tunneling work for the project.

    photCL SCE 12 - 00219

  • On Oct. 15. 1924. the 4 p.m. shift at Camp 60 established three records for hard rock tunneling

    On Oct. 15. 1924. the 4 p.m. shift at Camp 60 established three records for hard rock tunneling

    Visual Materials

    On Oct. 15, 1924, the 4 p.m. shift at Camp 60 established three records for hard rock tunneling. This hard-working crew drilled 30 feet in one shift, 174 feet in one (six-day) week, and amassed 692 feet for one entire month. These records stood until 1986 when they were surpassed by workers at Edison's Balsam Meadow Project. This photo shows Edison officials, including VP George C. Ward (5th from left) at the tunnel portal at Camp 60, reviewing the crew's progress.

    photCL SCE 12 - 00149

  • Image not available

    On March 28, 1985, the first of the two massive girders for the overhead crane in Balsam Meadow's underground powerhouse was raised into position

    Visual Materials

    On March 28, 1985, the first of the two massive girders for the overhead crane in Balsam Meadow's underground powerhouse was raised into position. The completion of this crane was a major milestone in the Balsam Meadow Project, for would be used to install the power stations heavy components.

    photCL SCE 12 - 00216

  • Big Creek Powerhouse #3

    Big Creek Powerhouse #3

    Visual Materials

    Big Creek Powerhouse #3 - Riveting section of 18' outlet pipe inside Tunnel 3, showing bracing, inside and outside the pipe to assure circular shape in preparation for placing concrete seal around pipe.

    photCL SCE 02 - 08934

  • This 1922 map shows the proposed ultimate development of the Big Creek Project to a size even larger than that first envisioned by John Eastwood

    This 1922 map shows the proposed ultimate development of the Big Creek Project to a size even larger than that first envisioned by John Eastwood

    Visual Materials

    This 1922 map shows the proposed ultimate development of the Big Creek Project to a size even larger than that first envisioned by John Eastwood. Still later plans added more powerhouses on the South Fork of the San Joaquin, but none were built before the depression ended work. Today, the Balsam Meadows Plant is near the site of old Powerhouse #5. Pg. 103.

    photCL SCE 11 - 00208

  • Image not available

    Highlights of 1986 - Century 2 Begins

    Manuscripts

    Format of original: VHS (See DVD copy) Run time: 26:08:00 SCE video discussing company highlights of 1986 as part of the company's "100 Years of Team Edison" campaign. Includes a recap of sales, employment, spending, and planning for the future of the company. Includes reports on the San Onofre Nuclear Generator, the Palo Verde station, the Mojave generating station, and the Balsam Meadow Project at Big Creek. Hosted by SCE Chairman Howard Allen.

    SCE MP 240