Visual Materials

Redondo Steam Plant



You might also be interested in

  • Redondo Steam Plant

    Redondo Steam Plant

    Visual Materials

    Redondo Steam Plant - pouring concrete for 4th turbine support.

    photCL SCE 05 - 53221

  • Redondo Beach Steam Station - Plant #1

    Redondo Beach Steam Station - Plant #1

    Visual Materials

    Redondo Beach Steam Station - Plant #1 - Looking west toward #1 turbine support. Concrete poured to air ejector floor. Final pour to Turbine Room floor scheduled for 7/22/1947.

    photCL SCE 02 - 29762

  • Redondo Beach Steam Station - Plant #1

    Redondo Beach Steam Station - Plant #1

    Visual Materials

    Redondo Beach Steam Station - Plant #1 - Looking west showing north end of #2 turbine support. Concrete poured to air ejector. Final pour for Turbine Room floor scheduled for 7/30/1947.

    photCL SCE 02 - 29761

  • Redondo Beach Steam Station - Plant #1

    Redondo Beach Steam Station - Plant #1

    Visual Materials

    Redondo Beach Steam Station - Plant #1 - Looking south showing form work on #2 turbine support. Concrete poured to air ejector floor. Final pour to Turbine Room floor scheduled for 7/30/1947.

    photCL SCE 02 - 29763

  • Redondo Beach Steam Station - Plant #1

    Redondo Beach Steam Station - Plant #1

    Visual Materials

    Redondo Beach Steam Station - Plant #1 - Looking northwest toward #2 turbine support. #1 turbine support in background.

    photCL SCE 02 - 29780

  • Redondo Beach Steam Station - Plant #1

    Redondo Beach Steam Station - Plant #1

    Visual Materials

    Redondo Beach Steam Station - Plant #1 - Looking southwest from operating floor toward #1 turbine support. #2 turbine support in background.

    photCL SCE 02 - 29779